Construction at our Five Farms campus has seen many big changes since the last update!
The temporary walls have been built in the Card Room and kitchen, which will help the construction team move forward with the following stages of Phase 1 construction. The most significant change is the removal of the stairwell between the Card Room and Tap Room! They have also continued the installation of the helical piles in the East Terrace Room area to make way for concrete to be poured in, and have started twisting helical piles into the ground where Main Grill Dining will be. Additionally, metal supports are being installed into the ground for the basement area and the kitchen subflooring has been removed due to excessive moisture.