The construction crew has been working hard with updates at our Five Farms campus!
The crew has built the wall framing on the Rooftop Terrace to differentiate the occupied terrace from the unoccupied spaces. In addition, they completed the bricklaying for the clubhouse addition. Next, they poured and smoothed the concrete for the area outside the Main Grille Dining room. The construction crew also dug into the ground to start the installation of a new gas service pipe. They have sprayed installation on the Outdoor Patio ceiling to maintain the R-value. Finally, they continued to install drywall and plywood in the clubhouse’s interior.