Last week’s beautiful weather has resulted in a lot of progress on the Five Farms construction site!
The construction crew completed the bricklaying on the chimney and walls, electrical, and waterproofing on the Rooftop Terrace. They have erected steel beams to support the roofing for the porches and worked on the columns on the existing porches to ensure stability. In addition, they poured and smoothed the concrete in the area between the Adirondack Bar and Foyer & Golfer’s Entry. The clubhouse addition has been laid with brick like the rest of the building.
The crew has been working on the framing for photos and ceilings throughout the clubhouse. Next, they installed the electrical and fire alarm lines. Finally, the Rooftop Terrace stairs are completed and waiting for the railing.