Last week’s spring/summer weather definitely helped with construction progress at our Five Farms campus!
The construction crew has started installing the roof sheathing, a layer of wood boards between the trusses and the final roofing. They also worked on the permanent roofing for the unoccupied terraces. In addition, the crew laid the brickwork for the loading dock. Other exterior updates included finishing ceiling framing for the Adirondack Bar, continuing the pavers’ demo, and starting the clean-up. As for the clubhouse interior, the Trophy Bar has seen exciting changes, including erecting the trophy wall and framing for the TVs. Finally, they have worked on the electrical rough-in, ductwork, and trim work throughout the clubhouse.