We are amazed by the Phase 1 construction progress week after week as exciting changes are being made.
The construction crew has installed the NanaWall in the Elm Room which allows the area to be an indoor/outdoor space. They started to place the ceramic tile in the Ladies’ Restroom and close the bulkhead trim with drywall in the 1924 Grille. Other interior updates include finishing the kitchen walling and closing the bar structure in the Trophy Bar.
As for the clubhouse exterior, the construction crew continued to finish the brickwork for the walkway and pedestrian walkway. They installed the sheathing for the porch ceilings and the roofing. Finally, they poured concrete for the loading dock.