The wintry conditions have not stopped the construction progress on our Five Farms campus!
The construction crew has cut a door opening and built the wall for the stairwell and future elevator shaft in the addition area. In the dining areas, they have begun ductwork and framing for the East Terrace Room, built the framing for the bar area in the Trophy Bar, and dug a trench in the Main Grill Dining area to install underground utilities: plumbing for soda and draft beer. The construction crew has also continued dry well installation near the Putting Green, which will detain stormwater (from the course facing the clubhouse) underground. Additionally, they have been working on the plumbing in the kitchen.