The construction crew has fabricated the exterior wall framing for the new Foyer and Golfer’s Entry, along with the new access to the Wine Room addition. The chimney between the Main Grille and Outdoor Patio areas is well underway. They had to cut access into the second level of the building to for the chimney access. Ductwork and electrical installation in the process of being installed.