Weekly Update 6.6-6.10

Seeing the progress made in the last week at our Five Farms construction site has been exciting!

The construction crew has built the framing for the main bar structure in the Trophy Bar. They have installed FRP panels to repel the kitchen’s stains and dirt. They have placed the wood on the stairs leading up to the Rooftop Terrace. Other interior updates include completing the wains coating in the Oak Room, painting throughout the clubhouse, and continuing to work on the lighting.

As for the clubhouse exterior, the construction crew has started to build the last wall for the loading dock. They have continued to build the trim for the roofing. In the Adirondack Bar, they worked on the rough-ins for lighting and fans. Finally, the crew began the installation of the new herringbone brick paved walkway.

Published by bcc1898

Baltimore Country Club was founded on January 12, 1898, at its Roland Park location.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: